Hyland/E. Oak Street Reconstruction Notice

Contractor plans to install traffic control this Wednesday July 20th (Midstate Traffic Control) with erosion control following. R.G. Schmitt plans to mobilize later this week and will be starting watermain on the southern end of the project working their way north. A second crew will join roughly a week and a half to two weeks later. Base course expected to start once all the utilities are completed which is anticipated the last week of August. Concrete, asphalt and sod restoration expected to follow and completed by the first week of October.